I’m building an extension to my house and have started the ground works, and the gas pipe is right in the way. When it’s all done the gas meter will be moved from it’s current location to the front of the house (pic taken from the back).
Apart from getting SGN to move it which they say can take 6 weeks, and running a new supply up to the loft for the boiler somehow, is there any other solution to this apart from be careful and don’t hit the pipe?
(It’s the steel pipe about 2’ off the house)
Apart from getting SGN to move it which they say can take 6 weeks, and running a new supply up to the loft for the boiler somehow, is there any other solution to this apart from be careful and don’t hit the pipe?
(It’s the steel pipe about 2’ off the house)